Hot Pour Rubberized Process |
PDF |
| Print | |
E-mail |
- Crack sealing to be completed on cracks 1/8" and larger. If there is vegetation in the cracks, a water-based weed killer should be applied at least one week prior to crack sealing.
- Clean cracks with a combination of power braided wire wheel, forced air and hand tools.
- Cracks must be dry before being filled. The temperature should be above 32ºF degrees.
- Fill cracks with rubberized crack sealant, such as Crafco 532 or equivalent. The sealant should be a hot-applied modified asphalt product heated in an oil-jacketed double boiler to 400ºF degrees and agitated. AC-20, roofing material, or any type of asphalt cut back is not acceptable.
- The material should be applied to the cracks with a walk-behind bander so it is flush with the pavement. The material should be banded a uniform width of approximately. 4 inches.
- Traffic should stay off of the fresh sealant for at least 15 minutes. If the area needs to be opened or is a high traffic area, the material should be dusted with black sand.
- If sealcoating is part of the project, the crack sealing should be completed prior to the sealcoating.
|